November 8 Rehab Update

posted in: Rehab Status | 0

November 1-8 Habitec Rehab Activity:

  • Contracts released and kick off meetings between Habitec and all consultants. (accounting contractual work)
  • Filing systems identified for the project team and proper file share set up. Team identification. Begin design development drawings set up.
  • Project management project kick off, creating a schedule for Habitec and all consultants, identification of all individuals involved, scheduling and hosting meetings for the entire team to get the project started.

Next steps will include:

  • Design development drawings to fully go underway
  • Architectural team design meetings to work through design details and areas that need further development
  • Working through design direction options with engineering team as well as contractor to identify options that also incorporate best cost effective direction.
  • Review and Finalization of RDL Contract

End of 11/15/24

Habitec’s reaches out to Fairbrae to either update on design direction, or identify options, and discuss any progress or important decisions that need client approval/direction/or to keep board informed

These items will be a major discussion at 11/18/24 Fairbrae Board Meeting